From self-delivery to expert-led scale
After a self-delivered 6-vehicle pilot, Brinks partnered with Zenobē to scale to 25 vehicles in 12 months, cutting costs and timelines whilst projecting $800k in fuel and maintenance savings.
>1.2m
kilometers covered per year
1,280 tons
CO2 carbon emissions avoided per year
10,000
passengers per week
Ventura, Victoria’s largest bus operator and charter coach operator, needed to develop Victoria’s first all-electric bus depot on a tight schedule. The operator received funding as part of the Victorian Government’s $20 million Zero Emission Bus Trials Program and wanted to ensure it deployed the funding for maximum value.
Alongside the tight schedule, there was a requirement to generate data and operational learnings which could drive future electric transport decision-making across the state.
Working with Ventura, Zenobē designed and then delivered the infrastructure to support 27 electric buses, including procurement and installation of 14 double-gun chargers; Low Voltage (LV) civil and electrical works; and management of High Voltage (HV) works on-site including installation of a new transformer and maintenance of the charging infrastructure for three years, ensuring Ventura has the charging availability required at all times.
Zenobē also installed its smart charging software, Hekaton, to capture and share key operational data with Ventura, which it can use for strategic planning and operational analysis.
At the time of construction, Ivanhoe became Victoria’s first all-electric depot and deployed the state’s largest fleet of locally-made zero-emission buses.
Ventura Bus has developed key insights and learnings about depot electrification that will put them in a good position to deliver on the Victorian government’s ZEB Transition Plan, whereby all new public transport buses purchased from 2025 will be ZEBs.
Ventura can focus on operating its fleet in the knowledge that Zenobē will take responsibility for the infrastructure to ensure service continuity.

After a self-delivered 6-vehicle pilot, Brinks partnered with Zenobē to scale to 25 vehicles in 12 months, cutting costs and timelines whilst projecting $800k in fuel and maintenance savings.

Discover how Zenobē is supporting Belgian bus operators with electrification with nearly 70 electric buses across multiple depots.

Zenobē partnered with Educational Bus Transportation (EBT), a managed entity of The Trans Group, to finance 10 electric school buses and deliver the associated charging infrastructure for Copiague Public Schools. The project supports New York State’s school bus electrification goals while providing zero-emission transport for approximately 4,500 students and creating a scalable foundation for future fleet expansion.
Thanks for getting in touch – we’ll respond as soon as possible. You can also reach us on contact@zenobe.com
Pete leads Zenobē’s growing team of Product specialists across all areas of the business. His team oversee our R&D as well as product development in both hardware and software.
He has been working in the European E-Mobility sector from over ten years, specialising in the design, build and delivery of software systems for EV Charging.