Ivanhoe: Victoria’s first all-electric bus depot

Ventura's all-electric bus fleet charging at the first fully electric bus depot in Victoria, designed and powered by Zenobē, showcasing innovative zero-emission public transport solutions.

Ventura, Victoria’s largest bus operator and charter coach operator, needed to develop Victoria’s first all-electric bus depot on a tight schedule. The operator received funding as part of the Victorian Government’s $20 million Zero Emission Bus Trials Program and wanted to ensure it deployed the funding for maximum value.

This included a requirement to generate data and operational learnings which could drive future electric transport decision-making across the state.

Solution

Working with Ventura, Zenobē designed and then delivered the infrastructure to support 27 electric buses, including:
  • Procurement and installation of 14 double-gun chargers
  • Low Voltage (LV) civil and electrical works
  • Management of High Voltage (HV) works on-site including installation of a new transformer and grid connection
  • Close collaboration with the Department of Transport and Planning (DTP)

A partner for the life of the charging infrastructure, Zenobē is contracted to operate and maintain the charging infrastructure for three years, ensuring Ventura has the charging availability required at all times.

Furthermore, Zenobē installed its smart charging software Hekaton to capture and share key operational data with Ventura, which it can use for strategic planning and operational analysis.

Key Results

  • Victoria’s first all-electric depot and the largest fleet of locally-made zero-emission buses deployed in Victoria (at the time of build).
  • Ventura Bus has developed key insights and learnings about depot electrification that will put them in a good position to deliver on the Victorian government’s ZEB Transition Plan whereby all new public transport buses purchased from 2025 will be ZEBs.
  • Ventura can focus on operating their fleet in the knowledge that Zenobē will take responsibility for the infrastructure to ensure service continuity.

In numbers

72994
>1.2m

kilometers covered per year

72994
1,280 tons

CO2 carbon emissions avoided per year

72994
10,000

passengers per week

Peter Smith

Head of Product

Pete leads Zenobē’s growing team of Product specialists across all areas of the business. His team oversee our R&D as well as product development in both hardware and software.

 

He has been working in the European E-Mobility sector from over ten years, specialising in the design, build and delivery of software systems for EV Charging.