Reducing diesel dependency for a nuclear power site

£23,000

saved in fuel costs

81%

reduction in fuel use

Portable power helps a site with limited grid access to reduce its carbon footprint.

Select Plant Hire logo
A row of Zenobē PowerSkid battery units outside the Zenobē Innovation Centre

The challenge

Sizewell C is one of the UK’s most significant nuclear infrastructure projects, and needed support during construction. With limited grid access, mobile BESS (Battery Energy Storage System) units were a suitable choice.

Larger projects more than ever need risks to be minimised, to avoid unwanted cost. At Sizewell C, construction and efficiency had to continue without interruptions. Reducing the carbon footprint was also high on the agenda.

The solution

Through its phases of construction, the site at Sizewell C required energy to run welfare cabins followed by temporary power for batching plants (concrete plants) on site. The Zenobē team devised a power deployment plan that matched project phases.

For a client that was focused on its net zero construction ambitions, using emission-free power units to massively reduce diesel generator use was a step in the right direction.

The outcome

The setup – a pair of 100kW/150kWh mobile BESS, paired with a 60kVA generator – together delivered a higher level of fuel efficiency that would otherwise be achieved by diesel generators alone. Prior reliance on diesel generators had led to high fuel use, particularly at low load conditions, which was inefficient and costly.

Select Plant Hire could reduce overheads for its client Laing O’Rourke through the smart use of power. Optimised power schedules and 24/7 monitoring ensured power output matched demand closely – saving money, and CO2.

“Partnering with Zenobē enables us to deploy innovative battery setups designed specifically to meet our customer's needs. The Zenobē team's battery expertise, deep product knowledge and close support, coupled with our specialist plant knowledge enables Select to provide clean and reliable power solutions for our customers.”
Ian Fleming
Product Leader, Select Site Solutions

Want to learn more? Contact us

Other Portable Power projects

Falcon Cranes

Discover how mobile BESS was deployed together with power management, to help Falcon Cranes reach new heights in its carbon-cutting ambitions.

Read More »

Contact us

Thanks for getting in touch – we’ll respond as soon as possible. You can also reach us on contact@zenobe.com

We will use your information to respond to your enquiry. For more information on how we handle your data, please see our privacy policy.

Peter Smith

Head of Product

Pete leads Zenobē’s growing team of Product specialists across all areas of the business. His team oversee our R&D as well as product development in both hardware and software.

 

He has been working in the European E-Mobility sector from over ten years, specialising in the design, build and delivery of software systems for EV Charging.